For mobility between Programme countries, the duration is at least 2 consecutive days excluding travel; for mobility between Programme and Partner countries, it is at least 5 consecutive days. In both cases, the maximum duration of the activity is 2 months.
In staff training mobility, if it is stated on the certificate of participation that the beneficiary carried out the activity for less than 2 days, except in cases of force majeure, the activity is considered invalid and no grant payment is made to the beneficiary.
Provided that the force majeure can be documented, activities in which the minimum duration could not be completed are accepted; a grant is awarded for the period spent, and travel expenses are paid based on the distance calculator. The Centre must be contacted before an event or situation can be considered as force majeure.